Title: Information Only Change Order: Multi Use Path (MUP) Reconstruction 2025 to Everlast Blacktop, of Elgin, Illinois.
Attachments: 1. Information Only - MUP Reconstruction 2025 - 614,803.42 - FINAL
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Information Only Change Order: Multi Use Path (MUP) Reconstruction 2025 to Everlast Blacktop, of Elgin, Illinois.

recommendation

Original Contract Amount:                                                                                                          $577,006.49

Current proposed Change Order:                                                                                     $37,796.93

Amended Contract Amount Total:                                           $614,803.42

The change order includes additional work required to achieve ADA compliance at roadway crossings along the multi-use path, including wider and longer curb ramps, additional concrete and detectable warning panels, and removal and replacement of unsuitable soil encountered during reconstruction of the Rote Road MUP. The funding source is the 1% Infrastructure Sales Tax.