title
Change Order: Whitman Street Reconstruction to N-Trak Group, of Loves Park, Illinois.
recommendation
Original Contract $9,614,440.27
Current Proposed Change Order $116,413.72
Amended Contract Total $9,730,853.99
The change order includes additional underground electrical work and pole relocation, hydrant relocation, tree removal and mobilization, exploratory earth excavation, retaining wall and handrail, irrigation installation, and storm sewer removal and installation. The funding source is the 1% Infrastructure Sales Tax.