Change Order: Activate Church Street and Main Street Two-Way Conversion (Supplemental #2) to GFT Infrastructure, Inc., of Chicago, Illinois.
recommendation
Original Contract Amount: $799,243.56
Previously approved Supplemental #1: $351,565.00
Current proposed Supplemental #2: $708,236.27
Amended Contract Amount Total: $1,859,044.83
The change order includes additional consultant services for right-of-way acquisition, appraisal and land acquisition negotiations, title commitments, and ROW plats for approximately 42 parcels along the corridor, as well as additional survey and design work required to address Illinois Department of Transportation (IDOT) review comments related to drainage plans, ADA ramps, and maintenance of traffic plans. The funding sources are the 1% Infrastructure Sales Tax and State of Illinois Jurisdictional Transfer Funds.